Successful installation of two offshore substation platforms and 20 jackets marks major milestone at the Moray East

Publication Date

DEME Offshore has successfully installed two of three offshore substation platforms (OSP) for the Moray East wind farm in the Moray Firth in Scotland. In the meantime jacket installation is also progressing with 20 jackets installed. The installation marks a major milestone in the progress of the construction of the 950 MW offshore wind farm.

DEME Offshore deployed a novel concept for this complex project, whereby the OSP jacket and wind turbine foundation design, construction and installation were fully aligned. Both offshore substation platforms were transported from the ENGIE yard in Hoboken, Belgium to the Port of Nigg in Scotland.

Under the management of DEME Offshore, which is the EPCI contractor, the first topside was installed by offshore installation vessel ‘Scylla’ early August , while the second topside has now also been successfully installed. DEME Offshore’s seamless installation of the topsides enables the construction of Moray East to swiftly proceed to the next phase and the follow-on activities such as the export cable works.

Jan Klaassen, Business Unit Director DEME Offshore, emphasises: “We are proud to have proven that combining the design, construction and installation of the offshore substation foundations and wind turbine foundations is clearly a workable solution for the industry, especially in an EPCI contract format. Both foundation types were designed in a similar way and fabricated with the same companies so that we could optimise synergies such as design teams, fabrication set-up, transport and installation tools. It all worked out as planned and designed, and crucially, resulted in significant direct cost and schedule benefits for the customer.

The fact that DEME Offshore is successfully installing both the substation platforms and jackets, despite the many exceptional complications brought by the Coronavirus pandemic and ongoing knock-on effects, highlights that we always do our utmost to fulfil the requirements of our Customers, whatever circumstances we face. We will continue to work closely with all the partners involved to deliver this project within these difficult circumstances.

Given the extensive scope and logistical challenges represented by this contract, DEME Offshore had made sure it was fully prepared well in advance of the start-up phase. We have dedicated a specialist team and significant management resources to this mammoth project to ensure operations are conducted to the highest safety and quality standards and that every detail is thoroughly considered before the next stage of the wind farm’s development.”
 

About DEME

DEME is a world leader in the highly specialised fields of dredging, solutions for the offshore energy industry, infra marine and environmental works. The company can build on more than 140 years of know-how and experience and has fostered a pioneering approach throughout its history, enabling it to be a front runner in innovation and new technologies.

DEME’s vision is to work towards a sustainable future by offering solutions for global challenges: a rising sea level, a growing population, reduction of CO2 emissions, polluted rivers and soils and the scarcity of natural resources.

While the company’s roots are in Belgium, DEME has built a strong presence in all of the world’s seas and continents, operating in more than 90 countries worldwide. DEME can rely on 5,200 highly skilled professionals across the globe. With a versatile and modern fleet of over 100 vessels, backed by a broad range of auxiliary equipment, the company can provide solutions for even the most complex projects.

DEME achieved a turnover of 2.62 billion euros in 2019.

 

For additional information:

Vicky Cosemans

Head of Communications DEME Group

Related jobs

All jobs